This page will be updated with Road Works Notices and Road Closure Notices for the above period.
N11
Safety related landscape management works are scheduled to take place between N11 Junction 7 (Bray South) and N11 Junction 11 (Kilpedder), from Tuesday 3rd to Friday 13th February.
Traffic management will be in place for the duration of the works, Tuesday to Friday (21:00 – 06:00).
Traffic Management:
Tuesday 3rd to Friday 13th February:
- N11 Southbound – Junction 7 to Junction 11 – Full Road Closure
-
- Diversion via N11 J7 / R768 / R761 / R774 / N11 J11
- N11 Southbound – Junction 9 – Entry Slip Closed
-
- Diversion via Ballydonagh Rd / Templecarrig Rd / Templecarrig Lower Rd / R761 / Blue Route
- N11 Southbound – Junction 8 – Entry Slip Closed
-
- Diversion via N11 NB / N11 J7 / Blue Route
- N11 Southbound – Herbert Rd – Entry Slip Closed
-
- Diversion via Kilbride Lane / R767 / N11 J7 / Blue Route
- N11 Southbound – Junction 7 to Junction 8 (Kilmacanogue) – Local Access Only
We apologise for any inconvenience.
Baltinglass MD
N81 Hollywood Cross Rural Traffic Calming Road Safety Improvement Scheme – Commencement of Roadworks
Glas Civil Engineering limited have been appointed by Wicklow County Council as works Contractor for the Construction Implementation and handover phases of the ‘N81 Hollywood Cross Rural Traffic Calming Road Safety Improvement Scheme’. The planned construction start date is Monday 21st of July and It is expected that these essential road safety works will be complete in Q1 of 2026.
Works include:
✓ Site clearance and enabling works
✓ Full depth road and footpath construction
✓ Road regulating and resurfacing works
✓ Installation of Bus Stops and associated infrastructure
✓ Construction of new drainage network,
✓ New kerb lines, tie ins and footpaths,
✓ Installation of 3 pedestrian crossings,
✓ Landscaping works,
✓ Installation of new line marking and road markings along the route
✓ Utility diversions
✓ Public Lighting
✓ All other ancillary work
During completion of the works, it will be necessary to make amendments to the existing road layout by the installation of temporary traffic management measures. Glas Civil Engineering limited will endeavour to minimise the disruption caused by these works, and we apologise in advance for any inconvenience that may be caused.
Greystones MD
Road Closure
Wicklow County Council wishes to advise that the undermentioned Road Closure will come into effect from Monday, 3rd November 2025 until Tuesday, 31st March 2026.
| Road to be Closed |
L-1027-1 Chapel Road, Delgany |
| Period of Closure |
Monday, 1st November 2025 to Tuesday, 31st March 2026 |
| Alternative Routes |
South Bound - Starts at the junction of Beechwood Park (L5220)/(L1027). South diversion is approx. 730m to roundabout at Delgany Wood. Drive 640m down Delgany Wood Avenue, turn left and continue 300m on Church Road until your reach the R761 North mini roundabout at Killincarrig. Turn left at the first exit and carry on 2.25km until you reach the Blacklion Manor Road. North Bound - The North diversion is 1km to the Blacklion Manor Road then follow the South diversion route vice versa. |
| Reason for Closure |
This closure is necessary to facilitate the Chapel Road Pedestrain and Cyclist Infrastructure Improvement Scheme. |